GCS was commissioned to carry out a dimensional survey and structural assessment of the warehouse within the building compound. The client would like to use the first floor of the warehouse as a restaurant / café.

The building was found with suspended timber floor joists, historical steel beams and cast-iron columns.

Structural assessments are carried out to determine the capacity of the members to ensure they are suitable for the proposed usage. Strengthening works and details were proposed to specific structural elements.

Similar Posts

  • Retaining Wall Inspection

    Project Information Project:Retaining Wall Inspection Category:Specific Structural Survey Summary We were commissioned by the client to carry out a specific structural survey of the retaining walls within the building plot. Following the surveyor’s report, concerns were raised on the structural integrity of 4 no. of retaining walls. The retaining walls were situated in front and…

  • Derby

    Project Information Project:Derby Category:Specific Structural Survey Summary We were commissioned by the client to carry out a specific structural survey of the building. The client has concerns about the structural integrity as various cracks were noticed to the external envelops and to the internal finishes. A specific structural survey report was produced to identify potential…

  • Abergavenny

    Project Information Project:Abergavenny Category:Structural Site Visit Summary We were commissioned by the client to carry out a site visit to determine the position of the load bearing walls. During the site visit, further advice and recommendations were given regarding the condition and safety of the structure.

  • Matlock

    Project Information Project:Matlock Category:Specific Structural Survey Summary We were commissioned by the client to carry out a specific structural survey of the front porch and front retaining wall to the building. The client had concerns on the structural integrity of the front porch as the condition had noticeably deteriorated in the past decade. A specific…